9th December 2007
Work gets under way
|
 |
| A temporary bridge
has to be built to provide access to site. The old one was destroyed when
the road was widenend. |
 |
| The Foundations
are built |
 |
|
28th December 2007
Snow arrives and work stops
for the winter
|
 |
|
30th March 2008
Work begins again
|
 |
| |
 |
| |
 |
|
14th April 2008
Work progresses well
|
 |
| |
 |
| |
 |
| |
 |
|
23rd May 2008
The roof is on!
|
 |
| |
 |
|
28th June 2008
Plasterboard is going onto
the inside walls
|
 |
| |
 |
| |
 |
| Inside
the electrics are being installed |
 |
|
1st October 2008
Living room
|
 |
| Kitchen |
 |
| Upstairs Bathroom |
 |
| Bedroom |
 |
|
14th October 2008
Leveling the ground
|
 |
| Electric is on! |
 |
|
April 2009
Starting to build the store
|
 |
| |
 |
|
August 2009
Starting to erect the fence
|
 |
| |
|