Early August 2001
Digging the foundations
|
 |
|
Week ending 25th August 2001
Putting in the foundations
|
 |
|
Week ending 1st September 2001
Erecting shuttering for walls
of ground floor
|
 |
|
Week ending 8th September 2001
The walls begin to go up!
|
 |
|
Week ending 15th September
2001
The walls continue to go up!
|
 |
|
Week ending 22nd September
2001
Inspite of heavy rain, building
work continues. The ground floor is now 50% complete!
|
 |
|
Week ending 29th September
2001
The building continues to grow - less rain this week!
|
 |
|
Week ending 6th October 2001
Some welcome sunshine helps building work this week!
|
 |
|
Week ending 21st October 2001
We are now nearing completion
and the ceiling of the ground floor is being put on
|
 |
|
Week ending 28th October 2001
Construction of the ceiling
continues
|
 |
|
Week ending 4th November 2001
Ground floor nearly complete
|
 |
|
Week ending 4th May 2002
Work under way on the first
floor
.
|
 |
|
Week ending 15th June 2002
Electricity is on its way to
the site
|
 |
|
Week ending 22nd June 2002
The roof to the first floor
is put on
|
 |
| Week
ending 30th June
Work starts on constructing
the rooms in the roof floor
|
 |
|
Week ending 14th July
Woodwork for the roof is being
erected
|
 |
|
Week ending 31st August
Woodwork for the roof continues.
Work is being hampered by heavy rains.
|
 |
|
Week ending 13th September
The woodwork of the roof is
nearly complete - Lindab starts to go on next week
|
 |
|
Week ending 28th September.
Work has been slow due to continuing
heavy rain. The woodwork for the roof and the anti-condensation foil has
been applied. Lindab will start to go on now.
|
 |
|
Thursday 3rd October.
The Lindab starts to go on
|
 |
|
Thursday 10th October
Work on the roof continues
well
|
 |
|
Wednesday 16th October 2002
A cold and misty day - but
the roof is on!
|
 |
|
Friday 18th October 2002
The roof is finished - rendering
of the walls continues
|
 |
|
Monday 21st October 2002
The sun is shining - rendering
of the walls continues
|
 |
|
Monday 28th October 2002
Rendering of the walls is nearly
complete - hopefully next week work on the doors and windows will start
|
 |
|
Thursday 14th November 2002
Rendering complete - Doors
& windows starting to go in
|
 |
|
Sunday 8th December 2002
More work done on top floor.
Windows continue to go in.
|
 |
|
Saturday 14th December 2002
Windows and doors are in; the
shell is complete!
Temperature now -18C &
work stops for the winter.
|
 |
|
Saturday 1st March 2003
Electrical installation begins
- top floor
|
 |
|
Saturday 8th March 2003
Electrical installation continues
- basement
|
 |
|
Saturday 10th May 2003
Internal doors and windows
are being made at a wood factory in Voronet
|
 |
|
Saturday 24th May 2003
Installation of internal doors
and windows begins
|
 |
|
Saturday 31st May 2003
Installation of internal floors
has begun
|
 |
|
Saturday 14th June 2003
Floor tiles have been put down
in some parts of the home
|
 |
|
Tuesday 8th July 2003
A fence is being built around
the care home.
|
 |
|
Tuesday 5th August 2003
The fence is now complete with
gate under construction - tiling and rendering continues inside.
|
 |
|
Saturday 23rd August 2003
External pipework is being
installed
|
 |
|
Friday 17th October 2003
Lots of work has been going
on inside - tiling is nearly complete. Lighting to go innext month. Painting
the outside of thebuilding is underway
|
 |
|
Friday 7th November 2003
Painting of the outside of
the building is complete
|
 |
|
Tuesday 11th November 2003
Steps and ramp to main entrance
are under construction
|
 |
|
Tuesday 9th December 2003
Electricity has arived on site
|
 |
|
Saturday 3rd April 2004
Work restarts. A bulldozer
has been on site all week leveling the land and landscaping
|
 |
|
Saturday 24th April 2004
Handrail to the entrance has
been installed
|
 |
|
Saturday 24th April 2004
A lot of work has been donw
leveling the ground around the home
|
 |
|
Saturday 24th April 2004
Bathroom fittings are being
installed
|
 |
|
Saturday 24th April 2004
Kitchen fittings are being
installed
|
 |
|
Saturday 24th April 2004
The heating is being installed
|
 |
|
Saturday 24th April 2004
Work on the cesspit, down the
hill from the home, is well under way
|
 |
|
Thursday 6th May 2004
Pipes are going in to link
nursing home and cesspit
|
 |
|
Thursday 6th May 2004
Topsoil is being places around
the building in preparation for the sowing of grass seed.
|
 |
|
Thursday 6th May 2004
The cesspit is nearly finished
|
 |
|
Monday 31st May 2004
Concrete tiles are being put
down on the drive.
|
 |
|
Friday 18th June 2004
The home is opened
|
 |