Project Ilisesti

Construction of the building :

Early August 2001

Digging the foundations

Week ending 25th August 2001

Putting in the foundations

Week ending 1st September 2001

Erecting shuttering for walls of ground floor

 

Week ending 8th September 2001

The walls begin to go up!

Week ending 15th September 2001

The walls continue to go up!

 

Week ending 22nd September 2001

Inspite of heavy rain, building work continues. The ground floor is now 50% complete!

Week ending 29th September 2001

The building continues to grow - less rain this week!

Week ending 6th October 2001

Some welcome sunshine helps building work this week!

Week ending 21st October 2001

We are now nearing completion and the ceiling of the ground floor is being put on

Week ending 28th October 2001

Construction of the ceiling continues

Week ending 4th November 2001

Ground floor nearly complete

 

Week ending 4th May 2002

Work under way on the first floor

.

 

Week ending 15th June 2002

Electricity is on its way to the site

Week ending 22nd June 2002

The roof to the first floor is put on

Week ending 30th June

Work starts on constructing the rooms in the roof floor

Week ending 14th July

Woodwork for the roof is being erected

Week ending 31st August

Woodwork for the roof continues. Work is being hampered by heavy rains.

Week ending 13th September

The woodwork of the roof is nearly complete - Lindab starts to go on next week

Week ending 28th September.

Work has been slow due to continuing heavy rain. The woodwork for the roof and the anti-condensation foil has been applied. Lindab will start to go on now.

Thursday 3rd October.

The Lindab starts to go on

Thursday 10th October

Work on the roof continues well

Wednesday 16th October 2002

A cold and misty day - but the roof is on!

Friday 18th October 2002

The roof is finished - rendering of the walls continues

Monday 21st October 2002

The sun is shining - rendering of the walls continues

Monday 28th October 2002

Rendering of the walls is nearly complete - hopefully next week work on the doors and windows will start

Thursday 14th November 2002

Rendering complete - Doors & windows starting to go in

Sunday 8th December 2002

More work done on top floor. Windows continue to go in.

Saturday 14th December 2002

Windows and doors are in; the shell is complete!

Temperature now -18C & work stops for the winter.

Saturday 1st March 2003

Electrical installation begins - top floor

Saturday 8th March 2003

Electrical installation continues - basement

Saturday 10th May 2003

Internal doors and windows are being made at a wood factory in Voronet

Saturday 24th May 2003

Installation of internal doors and windows begins

Saturday 31st May 2003

Installation of internal floors has begun

Saturday 14th June 2003

Floor tiles have been put down in some parts of the home

Tuesday 8th July 2003

A fence is being built around the care home.

Tuesday 5th August 2003

The fence is now complete with gate under construction - tiling and rendering continues inside.

Saturday 23rd August 2003

External pipework is being installed

Friday 17th October 2003

Lots of work has been going on inside - tiling is nearly complete. Lighting to go innext month. Painting the outside of thebuilding is underway

Friday 7th November 2003

Painting of the outside of the building is complete

Tuesday 11th November 2003

Steps and ramp to main entrance are under construction

Tuesday 9th December 2003

Electricity has arived on site

Saturday 3rd April 2004

Work restarts. A bulldozer has been on site all week leveling the land and landscaping

 

Saturday 24th April 2004

Handrail to the entrance has been installed

Saturday 24th April 2004

A lot of work has been donw leveling the ground around the home

Saturday 24th April 2004

Bathroom fittings are being installed

Saturday 24th April 2004

Kitchen fittings are being installed

Saturday 24th April 2004

The heating is being installed

Saturday 24th April 2004

Work on the cesspit, down the hill from the home, is well under way

Thursday 6th May 2004

Pipes are going in to link nursing home and cesspit

Thursday 6th May 2004

Topsoil is being places around the building in preparation for the sowing of grass seed.

Thursday 6th May 2004

The cesspit is nearly finished

Monday 31st May 2004

Concrete tiles are being put down on the drive.

Friday 18th June 2004

The home is opened